Earthworks
  • Clear site and Base Cut
  • Base Inspection (if Applicable) by Structural Engineer
  • Sand pad
  • Compaction Test by Structural Engineer
Site Services
  • Water available to building area
  • Power available to building area
Plumber
  • Pre-lay
Termite Contractor
  • Part A & Under-slab spray
Grano Worker
  • Concrete footings and slab, including mesh and membrane

1st Stage (Lock Up Kit) Delivery by Ross Squire Homes

Lock Up Carpenter
  • Erect wall frames, trusses and eaves / verandah framing
  • Roof cover
  • Install windows and external doors
  • External cladding
Plumber
  • Tube out
  • Drains
Electrician
  • Pre-wire

2nd Stage (Finishing Kit) Delivery by Ross Squire Homes (If applicable)

Plasterboard Fixer
  • Install insulation
  • Install ceiling and wall plasterboard
  • Install villaboard to wet areas
  • Advise Cabinet maker / Ross Squire Homes of dimensions prior to manufacture of cabinets
Cabinet Maker
  • Install Kitchen cabinets
  • Install Vanity cabinets (if cabinetmaker type)
Fixing Carpenter
  • Install door frames, doors, vanities (if pre made type), reveals, skirtings (if applicable)
Plumber
  • Sani/Tile set up (install Laundry trough, bath and puddle flanges in showers)
Tiler
  • Screed floors
  • Waterproof shower recesses, floors and walls
  • Lay floor and wall tiles, and then grout
  • Silicone shower recess, bath, above kitchen and vanity cabinets
Glazier
  • Measure shower screens and mirrors
Plumber
  • Plumbing finals (fitting and testing)
Electrician
  • Electrical finals (fitting and testing)
Glazier
  • Install shower screens and mirrors
Cleaner
  • Internal house clean
Earthworks
  • External site clean (if applicable)
Termite Contractor
  • Part B & Perimeter spray
Practical Completion
  • House complete
  • Contact Local Government Authority to Advise prior to occupancy